THE CATHEDRAL BELLS.

The Cathedral Bells, which were installed in their final position at the base of the central bell tower in 2004, continue to be rung. The temporary roof which was erected over the bells in 2004 has now been removed to allow for construction of the central tower, and a temporary enclosure has been built to protect the bells. They will continue to be rung during the whole period of the construction of the central bell tower.

Supporters can dedicate a gift to the building of the Tower.

For more information, contact:
+61(0)7 3835 2239 or complete the online donation enquiry form.

   
 
Completion Fund
 
LATEST CONSTRUCTION NEWS
as at July 2008.
 

On 1 March, to the applause of several hundred onlookers, the copper spires were lifted into place on the Western Towers . Crosses were then screwed into place and blessed by Bishop John from the cherry picker. This marked the beginning of the final stage of the completion of St John’s Cathedral.

The sandstone pinnacles at the corners of the towers have been completed. Louvres, made from north Queensland beech, are being inserted and leaded in place in the traditional manner and bird-proof netting is being installed. The scaffold will be progressively removed from the southern tower by the end of September while scaffold around the northern tower will be removed to roof level to allow continued access to the Central Tower construction.

Meanwhile work has progressed on the Central ( Bell ) Tower. More than half of the stonework has been erected. While this continues the roof is being constructed adjacent to the Cathedral. The main frame of the roof has been built of recycled timber including ironbark and spotted gum salvaged from the Albion Flour Mill. The framework is currently being sheeted with 19mm hoop pine ply. The next step is a waterproof membrane and finally the copper sheeting will be added. It is planned to lift the whole structure, a weight of 25 tonnes, into place in late November.

Prior to this, the two additional tenor bells purchased from Ayre and Smith in England will be positioned. This will increase the Cathedral bells to a peel of twelve. The design of the roof structure takes particular note of the acoustic requirements of the bells and the sound will be further managed by the inclusion of special adjustable baffles for use both during practice and full tolling.

All scaffolding will be removed by the end of February 2009.

 

LATEST CONSTRUCTION NEWS
as at Dec 2007
  Work commenced on the stonework for the two West End Towers in February 2007. With the aid of a tower crane the progress of work was rapid as the crane allowed individual stones to be laid directly onto the wall. (During previous stages of construction this was not possible due to the lack of available access for a crane). The two stone towers reached their maximum height in November 2007 and were topped with concrete slabs. They are presently awaiting their distinctive copper spires.
  The spires have been constructed on the ground nearby, and are currently being sheeted in copper. The completed spires are due to be lifted into position, again with the aid of a crane, in March 2008.
  The stonework for the central bell tower is now being cut and worked at the Chapter's Helidon quarry. The laying of the tower stone on site is to commence in February 2008 and be completed by the end of the year.
LATEST CONSTRUCTION NEWS
as at Dec 2006
  The Temporary Wall at the West End of the Nave is removed after 38 years in situ, revealing the completed interior of the West End
  Master Mason, Peter Dare, retires and returns to UK after overseeing the construction since 1990.
  At the quarry, about 30% of the stone required for the West End Towers, has been cut and is ready for the building to continue next year.
  The new Project Manager is Terry McCallum. See details in Pinnacle
LATEST CONSTRUCTION NEWS
as at Sept 2006
  The Stone vaulted ceiling is nearly complete above the narthex, making St John's the only fully stone vaulted ceiling in Australia.
  The walk way to the bell tower, above the ceiling, is now almost complete.
  Master Mason, Peter Dare, has completed the latest boss to be installed in the Donors' Gallery
  Work is on schedule to remove the last stages of the temporary wall, C1968, next month.
LATEST CONSTRUCTION NEWS
as at June 2006
  The last bay of the nave, above the narthex, is being completed before the ceiling can take shape and join the 1960's section of the nave.
  West wall of the north aisle nears completion. The nave section of the north wall is required from which to make adjustments to the existing roof.
  Work on diagonal ribs surrounding the Centenary Arch continues.
  Stone vaulting the roof of the last bay of the nave is due to commence. In place for this intricate work are the centreing, wooden frames, around which the rib arches and stone vaulting is placed.
LATEST CONSTRUCTION NEWS
as at March 2006
  Old temporary wall at the rear of the nave, built in 1968, has been removed so that the stone-vaulted ceiling can join north & south aisles.
  The North Tower has risen to the level of roof trusses and the weight of the existing roof is now carried by the building structure for the first time in 10 years.
  At the Quarry, stone has been cut for the Centenary Arch, the major arch above the Narthex.
  Scaffolding inside the cathdral has been removed now that the new temporary wall is built. There will be no need for scaffolding inside the cathedral again.
LATEST CONSTRUCTION NEWS
as at February 2006
  Scaffolding inside the nave is a welcome sign that the link between north & south aisle is underway. The stone-vaulting above the Narthex will begin soon.
LATEST CONSTRUCTION NEWS
as at December 2005
  Work begins on joining north & south aisles in the New Year.
  All lower arches of the north aisle are complete
  Base of North tower now complete up to tower floor level
  North West Wall of Nave growing at an amazing pace.
LATEST CONSTRUCTION NEWS
as at September 2005
  Focus of building site is now at the north aisle and tower.
  1/3rd of the tempoarary front, C1968, has been removed so that the 1960's section of the nave is linked with the new section.
  Tower walls are 50%complete.
  At the Quarry, stone is being prepared 6 months in advance for building.
  14 masons are working between the 2 sites: building site & quarry.
  Carpenter, Jack Barnes, continues building the handrails along the walkway over the ceiling to the central bell tower.
LATEST CONSTRUCTION NEWS
as at June 2005
  South West corner of the West End is now complete
  Removal of all scaffolding now allows the driveway and clear access to the West End to be used on special occasions.
  A tunnel has been constructed from the Porch to the existing Nave, allowing access beneath the remaining building site.
  The Great West Doors are in place. Woodwork by Jack Barnes, Ironwork by Robert Everingham.
  Grass planted outside the South West corner near the driveway.
  Floor of the tunnel contains permanent floor tiles of polished concrete to match the rest of the building.
  Northern Aisle construction is moving quickly.
  North Nave columns and arches are up to the top of the arch.
  The base of all walls is now built, completing the form of the cathedral as a structure.
LATEST CONSTRUCTION NEWS
as at Dec 2004
Peter Dare, Master Mason, is greatly encouraged by progress.

The West Facade is now complete, including all niches, and can be viewed free of scaffolding for the first time.

Internal space behind the West Facade is now completely enclosed.
Northern tower has begun. Both the weight-bearing column and the northern wall continue to grow.
Southern tower is complete to the point where work will cease at the beginning of mullions and jams for the louvre opening. A temporary roof covers the work so that it can be resumed at a later stage.
Quarry News
A second robot has been installed to increase the capacity for preparing stone. Technicians from Italy installed the computer program in December.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


The West End Towers reached their maximum height in Nov 07 and are now awaiting their distinctive copper spires.

 

 

 

completed interior of west end
View of the completed nave, after the West End was opened in Dec 06


Workmen begin stone vaulting the ceiling, between the rib arches.
Sept 06

 

 

 

 

 

 

Photo of north tower
Building the Northern Tower reaches roof level
March 2006

 

 

 

 

Temporary wall under cover ready for its demolition
Scaffolding in the nave to prepare a temporary wall for the duration of building the Ceiling over the Narthex
Feb 2006

photo of West front of Cathedral
West front of St John's Cathedral
April 2005

   
 

contacts & locator | faq's | donations | feedback | disclaimer | privacy

Last updated: 14 August 2008
© St John's Cathedral Completion Fund (2001-2007)